The Campus Community,

The College is undergoing modernization to its buildings and infrastructure. In the upcoming years over $170 Million dollars, addressing 22 capital projects, is projected to be spent by CUNY on our campus, a significant investment in the future of York. The campus has never experienced this level of capital improvement since its inception. 

Key highlights from projects underway and in the pipeline are as follows:


York College Capital Projects 2026 QTR 2 Update
Projects Ongoing- Being Built/ Filed
Status
Academic Core Building (ACB)
1
ACB Toilets ADA Upgrade
Phase 1 completed in June 2026, approximately 50% completion
17,000,000.00
2
Fire Alarm Upgrade
Project just started; below 5% completion
10,000,000.00
3
Emergency- ACB main Gas line leak repair
Worked performed via JOCs contract: 100% Complete
N/A
4
Sub-Basement groundwater grouting
Project just started; below 5% completion
500,000.00
5
ACB Water Dist. Sys Study
Project just started; below 5% completion
2,900,000.00
Performing Arts Center (PAC)
6
Interior & HVAC Upgrades
Overall at 65% completion 
40,000,000.00
7
Fire Alarm Upgrade
Project kickoff occurred; below 5% completion
3,800,000.00
8
Facade Leaks
Pending
200,000.00
Science Building (SB)
9
Certificate of Occupancy (C of O)
Completion after HVAC-Roof Replacement Project/ TCO will be in place pending completion of above work
250,000.00
Campus
10
159th Street DRI Walkway Upgrade
Scope includes new paving, seating, lighting and access gate, 65% completed 
1,000,000.00
Sub-Total 
75,650,000.00
Project Pipeline- Being designed/ prepared for bidding
Classroom Bldg.
11
Classroom Bldg. New Roof
Bid preparation
6,000,000.00
12
Window Replacement and Façade Restoration, interior upgrades
Bid preparation
3,000,000.00
13
MEP Upgrades 
Bid preparation
10,700,000.00
Science Building
14
RTU & Roof Replacement
Bid preparation
10,000,000.00
15
Window Replacement & Interior upgrades
Bid preparation
3,000,000.00
Track and Field
16
New Indoor Tennis Complex w/ covering
Procurement of design services
15,000,000.00
17
Field House upgrades, and subsurface drainage improvements
Procurement of design services
11,500,000.00
Campus wide
18
Perimeter Fencing & Exterior lighting
Bid preparation
8,800,000.00
19
Automatic Gates
Design Development
1,500,000.00
Sub-Total 
69,500,000.00
On the Horizon- Pre-Design
Campus Wide 
20
Updated Campus Master Plan 
Procurement of design services
1,500,000.00

21
Pre- Design: Exterior Façade & Windows
Design Development
16,500,000.00
22
Laboratory Fume Hood Replacement
Scope reconsideration 
8,100,000.00
Sub-Total 
26,100,000.00
Grand Total 
$171,250,000

We are looking forward to the progress and beautification of our campus.

Please do not hesitate to contact me with any questions.

Thank you,

Eduardo Rios                                                                  Office: 718-262-2104

Vice President for Finance & Administration           Cell: 929-720-2167