York College Capital Projects 2026 QTR 2 Update | ||||
Projects Ongoing- Being Built/ Filed | Status | |||
Academic Core Building (ACB) | ||||
1 | ACB Toilets ADA Upgrade | Phase 1 completed in June 2026, approximately 50% completion | 17,000,000.00 | |
2 | Fire Alarm Upgrade | Project just started; below 5% completion | 10,000,000.00 | |
3 | Emergency- ACB main Gas line leak repair | Worked performed via JOCs contract: 100% Complete | N/A | |
4 | Sub-Basement groundwater grouting | Project just started; below 5% completion | 500,000.00 | |
5 | ACB Water Dist. Sys Study | Project just started; below 5% completion | 2,900,000.00 | |
Performing Arts Center (PAC) | ||||
6 | Interior & HVAC Upgrades | Overall at 65% completion | 40,000,000.00 | |
7 | Fire Alarm Upgrade | Project kickoff occurred; below 5% completion | 3,800,000.00 | |
8 | Facade Leaks | Pending | 200,000.00 | |
Science Building (SB) | ||||
9 | Certificate of Occupancy (C of O) | Completion after HVAC-Roof Replacement Project/ TCO will be in place pending completion of above work | 250,000.00 | |
Campus | ||||
10 | 159th Street DRI Walkway Upgrade | Scope includes new paving, seating, lighting and access gate, 65% completed | 1,000,000.00 | |
Sub-Total | 75,650,000.00 | |||
Project Pipeline- Being designed/ prepared for bidding | ||||
Classroom Bldg. | ||||
11 | Classroom Bldg. New Roof | Bid preparation | 6,000,000.00 | |
12 | Window Replacement and Façade Restoration, interior upgrades | Bid preparation | 3,000,000.00 | |
13 | MEP Upgrades | Bid preparation | 10,700,000.00 | |
Science Building | ||||
14 | RTU & Roof Replacement | Bid preparation | 10,000,000.00 | |
15 | Window Replacement & Interior upgrades | Bid preparation | 3,000,000.00 | |
Track and Field | ||||
16 | New Indoor Tennis Complex w/ covering | Procurement of design services | 15,000,000.00 | |
17 | Field House upgrades, and subsurface drainage improvements | Procurement of design services | 11,500,000.00 | |
Campus wide | ||||
18 | Perimeter Fencing & Exterior lighting | Bid preparation | 8,800,000.00 | |
19 | Automatic Gates | Design Development | 1,500,000.00 | |
Sub-Total | 69,500,000.00 | |||
On the Horizon- Pre-Design | ||||
Campus Wide | ||||
20 | Updated Campus Master Plan | Procurement of design services | 1,500,000.00 | |
21 | Pre- Design: Exterior Façade & Windows | Design Development | 16,500,000.00 | |
22 | Laboratory Fume Hood Replacement | Scope reconsideration | 8,100,000.00 | |
Sub-Total | 26,100,000.00 | |||
Grand Total | $171,250,000 | |||
Eduardo Rios Office: 718-262-2104
Vice President for Finance & Administration Cell: 929-720-2167
Chief Financial Officer/ Chief Facilities Officer Email: erios9@PROTECTED
MS Teams: eduardo.rios09@PROTECTED
94-20 Guy R. Brewer Blvd. Jamaica, NY, 11451.