As part of the campus-wide Fiber Capital Project, York IT will begin Phase 1 remediation and upgrades of select wiring closets. This work will include network equipment updates designed to improve overall network reliability, performance, and accessibility across campus.

During each scheduled work window, computers, area WIFI antennas, and phones in the listed areas may temporarily lose network connectivity. Devices should automatically reconnect once the work is completed.
 
The Network Team will monitor each update closely and will only proceed to the next scheduled phase after confirming a successful implementation.
 
Phase 1 Wiring Closet Remediation Schedule
The work schedule is Thursday’s 6PM-11PM and Friday’s (we are close, but the work will continue) 9-5PM
 
Work Dates
Affected Wiring Closets / Areas
Thursday, June 25 – Friday, June 26
3F1, 3L, 3D
Thursday, July 2 – Monday, July 6
Holiday Week – No Work Scheduled
Thursday, July 9 – Friday, July 10
4G, 4D, 4F, 3G1, 3B, 3D
Thursday, July 16 – Friday, July 17
2F, 1G, 1E1
Thursday, July 23 – Friday, July 24
1D, 1L, 1T
Thursday, July 30 – Friday, July 31
1F2, CC-109, HP-2TE
 
Unless otherwise noted, the expected network impact window for each phase will begin on Thursday at 6:00 PM and continue through Friday at 5:00 PM. Each week affected departments will be notified. Classes that could be affected have already been notified and adjustment made.
 
No other service disruptions are expected. Email, web access, general internet connectivity, and centrally hosted systems such as CUNYfirst and Blackboard are expected to remain available and continue working as normal.
 
Please report any connectivity issues that occur outside of the scheduled update windows to the York IT Service Desk.
Thank you,
 
 
Greg Vega
Interim AVP/CIO
Information Technology York College